Creating a Dynamic Link or Linked Fields in Project
- Allan Rocha
- May 24, 2015
- 1 min read
Creating a Dynamic Link or Linked Fields in Project 2013.
Copy a normal cell (Ctrl+C)
Right click on the cell you want to paste the copied information
Select Paste Special

Select Paste Link and then OK

Change the value of the source cell,
in my case I just changed the duration to 5 days, which changed the finish date as well

you will see the value of the dynamic cell changing automatically
magic!!! 🙂
Seems that we can use this in many different cases… 🙂 Thanks for Alexandre Paiva in this post: