Creating a Dynamic Link or Linked Fields in Project 2013.
Copy a normal cell (Ctrl+C)
Right click on the cell you want to paste the copied information
Select Paste Special
![](https://static.wixstatic.com/media/db3ec0_37b1dbf5b08648f4b37c3bf67f43dd68~mv2.png/v1/fill/w_666,h_293,al_c,q_85,enc_auto/db3ec0_37b1dbf5b08648f4b37c3bf67f43dd68~mv2.png)
Select Paste Link and then OK
![](https://static.wixstatic.com/media/db3ec0_dfbe1465e46c48b880b64aa0d1dc773f~mv2.png/v1/fill/w_540,h_322,al_c,q_85,enc_auto/db3ec0_dfbe1465e46c48b880b64aa0d1dc773f~mv2.png)
Change the value of the source cell,
in my case I just changed the duration to 5 days, which changed the finish date as well
![](https://static.wixstatic.com/media/db3ec0_43c3a6cc77f7479f8c6b7a632834ef7c~mv2.png/v1/fill/w_635,h_199,al_c,q_85,enc_auto/db3ec0_43c3a6cc77f7479f8c6b7a632834ef7c~mv2.png)
you will see the value of the dynamic cell changing automatically
magic!!! 🙂
Seems that we can use this in many different cases… 🙂 Thanks for Alexandre Paiva in this post: