top of page
Writer's pictureAllan Rocha

Creating a Dynamic Link or Linked Fields in Project

Creating a Dynamic Link or Linked Fields in Project 2013.

  1. Copy a normal cell (Ctrl+C)

  2. Right click on the cell you want to paste the copied information

  3. Select Paste Special

  1. Select Paste Link and then OK

  1. Change the value of the source cell,

  2. in my case I just changed the duration to 5 days, which changed the finish date as well

  1. you will see the value of the dynamic cell changing automatically

  2. magic!!! 🙂


Seems that we can use this in many different cases… 🙂 Thanks for Alexandre Paiva in this post:

1 view0 comments

Comments


bottom of page